Construction of the east-west collector line and a 1000 cubic meter water tank in the green space

Amount of work

Working volume: 5500 meters, tank length: 1000 cubic meters

Project Details

Pipe material: polyethylene pipe, tank material: reinforced concrete tank

Project steps

Tubing with fiberglass pipes

Contract time

execution year : 1396
Execution time : 8 Month
Contract start date : 1396/02/04

Terms of the Contract

City : Isfahan
Contract Address : Isfahan, Tamdan Bridge, District 10 of Isfahan Municipality

Field of Expertise

Price list : Buildings, water distribution network, electrical facilities in 2015
Field of Expertise : Water, buildings, electrical installations