Implementation of a new pressure irrigation system

Amount of work

26 hectares

Project Details

Pressure irrigation network 300mm diameter concrete pipe Polyethylene pipe 315.200.160.110.90.75.63.40.16 Pump and pump equipment

Project steps

Implementation of a drip irrigation project

Contract time

execution year : 1402-1403
Execution time : Four months
Contract start date : 1402/11/17

Terms of the Contract

City : Isfahan
Contract Address : Isfahan, Zarinshah

Field of Expertise

Price list : Pressure irrigation in 2023
Field of Expertise : Implementation of a drip irrigation project

Image Gallery

GALLERY GALLERY GALLERY GALLERY