Construction of the wastewater transfer line from the treatment plant in the north of Isfahan to Shohada Eshtekar Square

Amount of work

Pipe laying 9200 meters long

Project Details

Fiberglass pipe with a diameter of 300 to 400 mm - type of pond: prefabricated concrete manhole

Project steps

Tubing with fiberglass pipes

Contract time

execution year : 1398
Execution time : 7 Month
Contract start date : 1398/10/05

Terms of the Contract

City : Isfahan
Contract Address : Isfahan, Fadak Street, District 14, Isfahan Municipality

Field of Expertise

Price list : Water distribution network 2018
Field of Expertise : Water and Wastewater