Vali Asr Shahin Shahr Wastewater
Project Pipe Laying of the Wastewater Transmission Line from the 1000 Cubic Meter Reservoir to the 10,000 Cubic Meter Vali Asr Reservoir
Client : Shahin Shahr Municipality
Urban Development Deputy Mayor
Amount of work
Work Volume: 8600 meters long
Project Details
Installation of fittings, valves, and a valve chamber
Construction of the Vali Asr Pumping Station building
Pipe material: GRP pipes
Pipe diameters: 600-800 mm
Project steps
Construction operations and GRP pipe laying
Contract time
execution year : 1394
Execution time : 6 Month
Contract start date : 1394/09/01
Terms of the Contract
City : Isfahan
Contract Address : Isfahan, Shahinshahr
Field of Expertise
Price list : Building, electrical and mechanical transmission line in 2016